Two Forks BESS
ERCOT-24INR0198BetaActiveBatteryERCOTLBNL + Live
309.8 MW storage in Cooke, TX · In queue since January 2022 · Proposed COD June 2027
309.8 MW
Capacity
1
Components
Battery
4y 3m
In Queue
IA Executed
IA Status
Signed May 2024
Interconnection Timeline
Queue → IA
2y 4m
IA → COD
3y 1m
Total Duration
2y 4m
Construction75%
Queue EntryJan 28, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementMay 3, 2024
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2027-06-30
Project Details
State
TX
County
Cooke
Region
ERCOT
Developer
Two Forks LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
684 SPRING 138kV
Data Source
LBNL + Live