Two Forks BESS — Project Summary

Queue ID
ERCOT-24INR0198
Capacity
309.8 MW
Technology
Battery
Status
active
Location
Cooke, TX
Region
ERCOT
Developer
Two Forks LLC
IA Status
IA Executed

Two Forks BESS

ERCOT-24INR0198BetaActiveBatteryERCOTLBNL + Live

309.8 MW storage in Cooke, TX · In queue since January 2022 · Proposed COD June 2027

309.8 MW

Capacity

1

Components

Battery

4y 3m

In Queue

IA Executed

IA Status

Signed May 2024

Interconnection Timeline

Queue → IA

2y 4m

IA → COD

3y 1m

Total Duration

2y 4m

Construction75%
Queue EntryJan 28, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementMay 3, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2027-06-30

Project Details

State

TX

County

Cooke

Region

ERCOT

Developer

Two Forks LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

684 SPRING 138kV

Data Source

LBNL + Live

No news available for this project.