Tehuacana Creek Solar SLF
ERCOT-24INR0188BetaActiveSolarERCOTLBNL + Live
505.5 MW generation in Navarro, TX · In queue since December 2021 · Proposed COD March 2027
505.5 MW
Capacity
1
Components
Solar
4y 4m
In Queue
—
IA Status
Signed Nov 2024
Interconnection Timeline
Queue → IA
2y 11m
IA → COD
2y 4m
Total Duration
2y 11m
Construction0%
Queue EntryDec 20, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementNov 25, 2024
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-03-10
Project Details
State
TX
County
Navarro
Region
ERCOT
Developer
—
Utility
—
Entity
ERCOT
Service Type
—
Data Source
LBNL + Live