Frio Farm
BetaActiveSolarERCOTLBNL + Live
106.5 MW generation in Frio, TX · In queue since December 2021 · Proposed COD June 2026
106.5 MW
Capacity
1
Components
Solar
4y 3m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
4y 6m
Facilities Study50%
Queue EntryDec 20, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-06-25
Project Details
State
TX
County
Frio
Region
ERCOT
Developer
PREMIER ENGINEERING USA CORP.
Utility
—
Entity
ERCOT
Point of Interconnection
8221 BIG FOOT4A 138kV
Data Source
LBNL + Live
No news available for this project.