Bowhead Storage
BetaActiveBatteryERCOTLBNL
40 MW storage in Kleberg, TX · In queue since December 2021 · Proposed COD January 2026
40 MW
Capacity
1
Components
Battery
4y 3m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
4y 1m
Schedule
2 months past proposed COD
Facilities Study50%
Queue EntryDec 3, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-01-15
Project Details
State
TX
County
Kleberg
Region
ERCOT
Developer
Baffin Bay Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV 8519 Kleberg _x0013_ 8518 Kingsville
Data Source
LBNL