Solar Star North Herty Storage
BetaActiveBatteryERCOTLBNL + Live
125.4 MW storage in Angelina, TX · In queue since February 2022 · Proposed COD August 2027
125.4 MW
Capacity
1
Components
Battery
4y 1m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5y 6m
Facilities Study50%
Queue EntryFeb 21, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-08-25
Project Details
State
TX
County
Angelina
Region
ERCOT
Developer
Solar Star North Herty Storage, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
3319 Redland Switch 138 kV
Data Source
LBNL + Live