Smith Lake Solar DC
ERCOT-24INR0172BetaActiveSolarERCOTLBNL + Live
402 MW generation in Grimes, TX · In queue since February 2022 · Proposed COD December 2028
402 MW
Capacity
1
Components
Solar
4y 2m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
6y 10m
Facilities Study50%
Queue EntryFeb 7, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-29
Project Details
State
TX
County
Grimes
Region
ERCOT
Developer
Smith Lake Solar
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
TAP 345 KV 44645 SINGLETON - 44900 ZENITH Ckt #99
Data Source
LBNL + Live
No news available for this project.