OCI SunRoper
ERCOT-24INR0167BetaActiveSolarERCOTLBNL + Live
265.1 MW generation in Wharton, TX · In queue since November 2021 · Proposed COD October 2027
265.1 MW
Capacity
1
Components
Solar
4y 5m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5y 11m
Facilities Study50%
Queue EntryNov 24, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-10-01
Project Details
State
TX
County
Wharton
Region
ERCOT
Developer
OCI SunRoper LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap138kV #43190 South Lane City to #42985 Dyann CKT#60
Data Source
LBNL + Live
Linked EIA Plant
OCI SunRoper
EIA Plant ID: 65893