Merope BESS
BetaActiveBatteryERCOTLBNL + Live
401.92 MW storage in Comanche, TX · In queue since December 2021 · Proposed COD March 2028
401.92 MW
Capacity
1
Components
Battery
4y 3m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
6y 3m
Facilities Study50%
Queue EntryDec 20, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-03-01
Project Details
State
TX
County
Comanche
Region
ERCOT
Developer
BRP Merope BESS LLC
Utility
—
Entity
ERCOT
Point of Interconnection
345 kV Corn Trail Switch Substation (#11441)
Data Source
LBNL + Live