Moonstone Solar Project
ERCOT-24INR0156BetaActiveSolarERCOTLBNL + Live
145.81 MW generation in Wilson, TX · In queue since October 2021 · Proposed COD March 2029
145.81 MW
Capacity
1
Components
Solar
4y 6m
In Queue
Facility Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
7y 5m
Facilities Study50%
Queue EntryOct 27, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-03-31
Project Details
State
TX
County
Wilson
Region
ERCOT
Developer
Ignis TX Solar One LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV Eagle Creek (5132) to Floresville (5155)
Data Source
LBNL + Live
No news available for this project.