Lupinus Storage 2 — Project Summary

Queue ID
ERCOT-24INR0155
Capacity
122.92 MW
Technology
Battery
Status
active
Location
Franklin, TX
Region
ERCOT
Developer
Lupinus Solar 2, LLC
IA Status
Facility Study

Lupinus Storage 2

ERCOT-24INR0155BetaActiveBatteryERCOTLBNL + Live

122.92 MW storage in Franklin, TX · In queue since December 2021 · Proposed COD April 2027

122.92 MW

Capacity

1

Components

Battery

4y 4m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

5y 4m

Facilities Study50%
Queue EntryDec 13, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-04-03

Project Details

State

TX

County

Franklin

Region

ERCOT

Developer

Lupinus Solar 2, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

1794 Monticello Tap Substation 138 kV

Data Source

LBNL + Live

No news available for this project.