Calpine Guadalupe Peakers
BetaActiveGasERCOTLBNL + Live
450 MW generation in Guadalupe, TX · In queue since November 2021 · Proposed COD May 2027
450 MW
Capacity
1
Components
Gas
4y 4m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5y 6m
Facilities Study50%
Queue EntryNov 15, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-05-23
Project Details
State
TX
County
Guadalupe
Region
ERCOT
Developer
Guadalupe Peaking Energy Center, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
7044 Marion 345kV
Data Source
LBNL + Live
No news available for this project.