Gaia Solar
ERCOT-24INR0141BetaActiveSolarERCOTLBNL + Live
152.65 MW generation in Navarro, TX · In queue since December 2021 · Proposed COD May 2026
152.65 MW
Capacity
1
Components
Solar
4y 4m
In Queue
IA Executed
IA Status
Signed Nov 2023
Interconnection Timeline
Queue → IA
1y 11m
IA → COD
2y 6m
Total Duration
1y 11m
Construction75%
Queue EntryDec 29, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementNov 8, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-05-01
Project Details
State
TX
County
Navarro
Region
ERCOT
Developer
Gaia Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 3127 Trinidad SES - 3454 Montfort Switch
Data Source
LBNL + Live