Midpoint Solar
98.3 MW generation in Hill, TX · In queue since October 2021 · Proposed COD March 2026
98.3 MW
Capacity
1
Components
Solar
4y 6m
In Queue
IA Executed
IA Status
Signed Oct 2023
Queue → IA
2 years
IA → COD
2y 5m
Total Duration
2 years
Schedule
1 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-03-13
State
TX
County
Hill
Region
ERCOT
Developer
Midpoint Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
138 KV Tap #3518 BLUM to #237 Blanton
Data Source
LBNL + Live