Midpoint Storage — Project Summary

Queue ID
ERCOT-24INR0138
Capacity
50.9 MW
Technology
Battery
Status
active
Location
Hill, TX
Region
ERCOT
Developer
Midpoint Solar, LLC
IA Status
IA Executed

Midpoint Storage

ERCOT-24INR0138BetaActiveBatteryERCOTLBNL + Live

50.9 MW storage in Hill, TX · In queue since October 2021 · Proposed COD March 2026

50.9 MW

Capacity

1

Components

Battery

4y 6m

In Queue

IA Executed

IA Status

Signed Oct 2023

Interconnection Timeline

Queue → IA

2 years

IA → COD

2y 5m

Total Duration

2 years

Schedule

1 months past proposed COD

Construction75%
Queue EntryOct 15, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementOct 31, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2026-03-13

Project Details

State

TX

County

Hill

Region

ERCOT

Developer

Midpoint Solar, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

138 KV Tap #3518 BLUM to #237 Blanton

Data Source

LBNL + Live

No news available for this project.