Bowhead Solar — Project Summary

Queue ID
ERCOT-24INR0132
Capacity
165 MW
Technology
Solar
Status
active
Location
Kleberg, TX
Region
ERCOT
Developer
Baffin Bay Solar, LLC
IA Status
Facility Study

Bowhead Solar

BetaActiveSolarERCOTLBNL

165 MW generation in Kleberg, TX · In queue since November 2021 · Proposed COD January 2026

165 MW

Capacity

1

Components

Solar

4y 4m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

4y 2m

Schedule

2 months past proposed COD

Facilities Study50%
Queue EntryNov 16, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-01-15

Project Details

State

TX

County

Kleberg

Region

ERCOT

Developer

Baffin Bay Solar, LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap 138kV 8519 Kleberg _x0013_ 8518 Kingsville

Data Source

LBNL