High Noon Solar
ERCOT-24INR0124BetaActiveSolarERCOTLBNL + Live
182 MW generation in Hill, TX · In queue since November 2021 · Proposed COD May 2028
182 MW
Capacity
1
Components
Solar
4y 5m
In Queue
IA Executed
IA Status
Signed May 2024
Interconnection Timeline
Queue → IA
2y 6m
IA → COD
4 years
Total Duration
2y 6m
Construction75%
Queue EntryNov 3, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementMay 3, 2024
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2028-05-09
Project Details
State
TX
County
Hill
Region
ERCOT
Developer
High Noon Solar Project, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 445 Yates - 444 Covington
Data Source
LBNL + Live
No news available for this project.