PHOTO BESS 1
BetaActiveBatteryERCOTLBNL + Live
75 MW storage in Uvalde, TX · In queue since October 2021 · Proposed COD September 2027
75 MW
Capacity
1
Components
Battery
4y 5m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5y 11m
Facilities Study50%
Queue EntryOct 29, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-09-01
Project Details
State
TX
County
Uvalde
Region
ERCOT
Developer
CED Development Inc.
Utility
—
Entity
ERCOT
Point of Interconnection
5885 Downie 138kV
Data Source
LBNL + Live
No news available for this project.