Utley Solar
ERCOT-24INR0117BetaActiveSolarERCOTLBNL + Live
221.78 MW generation in Freestone, TX · In queue since September 2021 · Proposed COD May 2028
221.78 MW
Capacity
1
Components
Solar
4y 7m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
6y 8m
Facilities Study50%
Queue EntrySep 7, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-05-11
Project Details
State
TX
County
Freestone
Region
ERCOT
Developer
Palmera Solar Development LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 3381 Big Brown Switch - 3391 Jewett
Data Source
LBNL + Live
No news available for this project.