Kildare
BetaActiveSolarERCOTLBNL + Live
70 MW generation in Jackson, TX · In queue since January 2022 · Proposed COD September 2026
70 MW
Capacity
1
Components
Solar
4y 2m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
4y 8m
Facilities Study50%
Queue EntryJan 28, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-09-30
Project Details
State
TX
County
Jackson
Region
ERCOT
Developer
Galsol, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
5524 Cordele 69 Sub 69 kV
Data Source
LBNL + Live