Oriana BESS
ERCOT-24INR0109BetaActiveBatteryERCOTLBNL + Live
60.3 MW storage in Victoria, TX · In queue since August 2021 · Proposed COD October 2028
60.3 MW
Capacity
1
Components
Battery
4y 8m
In Queue
IA Executed
IA Status
Signed Feb 2023
Interconnection Timeline
Queue → IA
1y 6m
IA → COD
5y 8m
Total Duration
1y 6m
Construction75%
Queue EntryAug 25, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementFeb 27, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2028-10-30
Project Details
State
TX
County
Victoria
Region
ERCOT
Developer
Oriana Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 5502 Rayburn - 5584 Vanderbilt
Data Source
LBNL + Live
No news available for this project.