Opuntia Solar SLF — Project Summary

Queue ID
ERCOT-24INR0103
Capacity
102.04 MW
Technology
Solar
Status
active
Location
Refugio, TX
Region
ERCOT
Developer
Opuntia Solar, LLC
IA Status
Facility Study

Opuntia Solar SLF

BetaActiveSolarERCOTLBNL

102.04 MW generation in Refugio, TX · In queue since August 2021 · Proposed COD March 2028

102.04 MW

Capacity

1

Components

Solar

4y 7m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

6y 7m

Facilities Study50%
Queue EntryAug 24, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-03-10

Project Details

State

TX

County

Refugio

Region

ERCOT

Developer

Opuntia Solar, LLC

Utility

Entity

ERCOT

Point of Interconnection

tap 138kV 5607 Warburton - 8912 Medio Creek

Data Source

LBNL

No news available for this project.