Opuntia Solar SLF
BetaActiveSolarERCOTLBNL
102.04 MW generation in Refugio, TX · In queue since August 2021 · Proposed COD March 2028
102.04 MW
Capacity
1
Components
Solar
4y 7m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
6y 7m
Facilities Study50%
Queue EntryAug 24, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-03-10
Project Details
State
TX
County
Refugio
Region
ERCOT
Developer
Opuntia Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
tap 138kV 5607 Warburton - 8912 Medio Creek
Data Source
LBNL
No news available for this project.