Val Vista Grid BESS 2 — Project Summary

Queue ID
ERCOT-24INR0102
Capacity
210.56 MW
Technology
Battery
Status
active
Location
Hidalgo, TX
Region
ERCOT
Developer
Val Vista Grid, LLC
IA Status
Facility Study

Val Vista Grid BESS 2

ERCOT-24INR0102BetaActiveBatteryERCOTLBNL + Live

210.56 MW storage in Hidalgo, TX · In queue since October 2021 · Proposed COD March 2029

210.56 MW

Capacity

1

Components

Battery

4y 6m

In Queue

Facility Study

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

7y 5m

Facilities Study50%
Queue EntryOct 1, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-03-30

Project Details

State

TX

County

Hidalgo

Region

ERCOT

Developer

Val Vista Grid, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 345kV 8383 North Edinburg - 80137 Stewart Road

Data Source

LBNL + Live

No news available for this project.