BRP Volga BESS — Project Summary

Queue ID
ERCOT-24INR0096
Capacity
174.63 MW
Technology
Battery
Status
active
Location
Dallas, TX
Region
ERCOT
Developer
BRP Volga BESS LLC
IA Status
Facility Study

BRP Volga BESS

BetaActiveBatteryERCOTLBNL

174.63 MW storage in Dallas, TX · In queue since December 2021 · Proposed COD December 2027

174.63 MW

Capacity

1

Components

Battery

4y 3m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

6 years

Facilities Study50%
Queue EntryDec 20, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-01

Project Details

State

TX

County

Dallas

Region

ERCOT

Developer

BRP Volga BESS LLC

Utility

Entity

ERCOT

Point of Interconnection

138 kV Seagoville Switch Substation (#2434; ONCOR)

Data Source

LBNL

No news available for this project.