Dovetail Solar 2
BetaActiveSolarERCOTLBNL + Live
666.1 MW generation in Jack, TX · In queue since October 2021 · Proposed COD April 2029
666.1 MW
Capacity
1
Components
Solar
4y 5m
In Queue
Facility Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
7y 6m
Facilities Study50%
Queue EntryOct 26, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-04-20
Project Details
State
TX
County
Jack
Region
ERCOT
Developer
Hecate Energy Dovetail Solar 2 LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345 KV 1421 Willow Creek - 60515 Clear Crossing
Data Source
LBNL + Live
No news available for this project.