Dovetail Solar 1 — Project Summary

Queue ID
ERCOT-24INR0094
Capacity
666.1 MW
Technology
Solar
Status
active
Location
Jack, TX
Region
ERCOT
Developer
Hecate Energy Dovetail Solar 1 LLC
IA Status
Facility Study

Dovetail Solar 1

BetaActiveSolarERCOTLBNL + Live

666.1 MW generation in Jack, TX · In queue since September 2021 · Proposed COD April 2027

666.1 MW

Capacity

1

Components

Solar

4y 6m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

5y 7m

Facilities Study50%
Queue EntrySep 21, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-04-15

Project Details

State

TX

County

Jack

Region

ERCOT

Developer

Hecate Energy Dovetail Solar 1 LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap 345 KV 1421 Willow Creek - 60515 Clear Crossing Ckt 2

Data Source

LBNL + Live