Dovetail Solar 1
BetaActiveSolarERCOTLBNL + Live
666.1 MW generation in Jack, TX · In queue since September 2021 · Proposed COD April 2027
666.1 MW
Capacity
1
Components
Solar
4y 6m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5y 7m
Facilities Study50%
Queue EntrySep 21, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-04-15
Project Details
State
TX
County
Jack
Region
ERCOT
Developer
Hecate Energy Dovetail Solar 1 LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345 KV 1421 Willow Creek - 60515 Clear Crossing Ckt 2
Data Source
LBNL + Live
No news available for this project.