Oriana Solar
BetaActiveSolarERCOTLBNL
181 MW generation in Victoria, TX · In queue since August 2021 · Proposed COD April 2025
181 MW
Capacity
1
Components
Solar
4y 7m
In Queue
IA Executed
IA Status
Signed Feb 2023
Interconnection Timeline
Queue → IA
1y 6m
IA → COD
2y 2m
Total Duration
1y 6m
Schedule
12 months past proposed COD
Construction75%
Queue EntryAug 25, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementFeb 27, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2025-04-06
Project Details
State
TX
County
Victoria
Region
ERCOT
Developer
Oriana Solar LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV 5502 Rayburn - 5584 Vanderbilt
Data Source
LBNL
No news available for this project.