BRP Springbok Solar
BetaActiveSolarERCOTLBNL
202.39 MW generation in Hale, TX · In queue since August 2021 · Proposed COD December 2027
202.39 MW
Capacity
1
Components
Solar
4y 7m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
6y 4m
Facilities Study50%
Queue EntryAug 25, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-01
Project Details
State
TX
County
Hale
Region
ERCOT
Developer
Antelope Solar LLC
Utility
—
Entity
ERCOT
Point of Interconnection
23920 Blackwater Draw Switching Station 345kV
Data Source
LBNL