Tres Margaritas Solar
BetaActiveSolarERCOTLBNL
60.95 MW generation in Dimmit, TX · In queue since July 2021 · Proposed COD June 2026
60.95 MW
Capacity
1
Components
Solar
4y 8m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
4y 11m
Facilities Study50%
Queue EntryJul 13, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-06-30
Project Details
State
TX
County
Dimmit
Region
ERCOT
Developer
Gransolar Texas Six, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV 8613 Big Wells _x0013_ 8212 Dilley Switching Station
Data Source
LBNL
No news available for this project.