Pisgah Ridge Storage 3 — Project Summary

Queue ID
ERCOT-24INR0087
Capacity
101.36 MW
Technology
Battery
Status
active
Location
Navarro, TX
Region
ERCOT
Developer
Pisgah Ridge 3, LLC
IA Status
Facility Study

Pisgah Ridge Storage 3

BetaActiveBatteryERCOTLBNL + Live

101.36 MW storage in Navarro, TX · In queue since July 2021 · Proposed COD December 2028

101.36 MW

Capacity

1

Components

Battery

4y 8m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

7y 5m

Facilities Study50%
Queue EntryJul 14, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-01

Project Details

State

TX

County

Navarro

Region

ERCOT

Developer

Pisgah Ridge 3, LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap 345kV 68091 Navarro - 46020 Limestone

Data Source

LBNL + Live

No news available for this project.