Pisgah Ridge Solar 2
BetaActiveSolarERCOTLBNL + Live
101.89 MW generation in Navarro, TX · In queue since July 2021 · Proposed COD December 2028
101.89 MW
Capacity
1
Components
Solar
4y 8m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
7y 5m
Facilities Study50%
Queue EntryJul 14, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-01
Project Details
State
TX
County
Navarro
Region
ERCOT
Developer
Pisgah Ridge Solar 2, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kV 68091 Navarro - 46020 Limestone
Data Source
LBNL + Live
No news available for this project.