SANJAC BESS
BetaActiveBatteryERCOTLBNL + Live
202.37 MW storage in Harris, TX · In queue since July 2021 · Proposed COD April 2027
202.37 MW
Capacity
1
Components
Battery
4y 8m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5y 9m
Facilities Study50%
Queue EntryJul 8, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-04-04
Project Details
State
TX
County
Harris
Region
ERCOT
Developer
Castleman Power
Utility
—
Entity
ERCOT
Point of Interconnection
40270 Riverside 138kV
Data Source
LBNL + Live
No news available for this project.