SANJAC BESS — Project Summary

Queue ID
ERCOT-24INR0081
Capacity
202.37 MW
Technology
Battery
Status
active
Location
Harris, TX
Region
ERCOT
Developer
Castleman Power
IA Status
Facility Study

SANJAC BESS

BetaActiveBatteryERCOTLBNL + Live

202.37 MW storage in Harris, TX · In queue since July 2021 · Proposed COD April 2027

202.37 MW

Capacity

1

Components

Battery

4y 8m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

5y 9m

Facilities Study50%
Queue EntryJul 8, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-04-04

Project Details

State

TX

County

Harris

Region

ERCOT

Developer

Castleman Power

Utility

Entity

ERCOT

Point of Interconnection

40270 Riverside 138kV

Data Source

LBNL + Live

No news available for this project.