Boxcar Solar 2
BetaActiveSolarERCOTLBNL
251.3 MW generation in Ellis, TX · In queue since July 2021 · Proposed COD September 2027
251.3 MW
Capacity
1
Components
Solar
4y 8m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
6y 2m
Facilities Study50%
Queue EntryJul 13, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-09-30
Project Details
State
TX
County
Ellis
Region
ERCOT
Developer
EDF Renewables Development, Inc.
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345 kV 1907 Venus N - 68091 Navarro