Apogee Wind II
BetaActiveWindERCOTLBNL + Live
47.25 MW generation in Throckmorton, TX · In queue since July 2021 · Proposed COD March 2027
47.25 MW
Capacity
1
Components
Wind
4y 8m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5y 8m
Facilities Study50%
Queue EntryJul 13, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-03-31
Project Details
State
TX
County
Throckmorton
Region
ERCOT
Developer
King Creek Wind Farm 3, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
60791 Perigee Substation 345kV
Data Source
LBNL + Live