Sypert Branch Solar Project
261.15 MW generation in Milam, TX · In queue since September 2021 · Proposed COD April 2026
261.15 MW
Capacity
1
Components
Solar
4y 7m
In Queue
IA Executed
IA Status
Signed Oct 2023
Queue → IA
2y 1m
IA → COD
2y 6m
Total Duration
2y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-04-30
State
TX
County
Milam
Region
ERCOT
Developer
Sypert Branch Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV #3751 Scooter Switch - #3687 Bell County East Switch Ckt 2
Data Source
LBNL + Live