Triple B Solar Alt#2
BetaActiveSolarERCOTLBNL + Live
150 MW generation in Lampasas, TX · In queue since June 2021 · Proposed COD July 2027
150 MW
Capacity
1
Components
Solar
4y 9m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
6y 1m
Facilities Study50%
Queue EntryJun 10, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-07-01
Project Details
State
TX
County
Lampasas
Region
ERCOT
Developer
Triple B Solar LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV 7066 Adamsville - 7064 Lampasas
Data Source
LBNL + Live
No news available for this project.