Eighteenmile Solar SLF — Project Summary

Queue ID
ERCOT-24INR0061
Capacity
153.06 MW
Technology
Solar
Status
active
Location
Goliad, TX
Region
ERCOT
Developer
Weser Solar, LLC
IA Status
Facility Study

Eighteenmile Solar SLF

BetaActiveSolarERCOTLBNL

153.06 MW generation in Goliad, TX · In queue since August 2021 · Proposed COD December 2026

153.06 MW

Capacity

1

Components

Solar

4y 7m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

5y 4m

Facilities Study50%
Queue EntryAug 18, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-01

Project Details

State

TX

County

Goliad

Region

ERCOT

Developer

Weser Solar, LLC

Utility

Entity

ERCOT

Point of Interconnection

Tap 138kV 5730 Four Corners - 5728 Choate

Data Source

LBNL

No news available for this project.