Cuchillas Solar
ERCOT-24INR0059BetaActiveSolarERCOTLBNL + Live
305.6 MW generation in Webb, TX · In queue since June 2021 · Proposed COD December 2028
305.6 MW
Capacity
1
Components
Solar
4y 10m
In Queue
IA Executed
IA Status
Signed Jun 2023
Interconnection Timeline
Queue → IA
2 years
IA → COD
5y 6m
Total Duration
2 years
Construction75%
Queue EntryJun 2, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementJun 20, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2028-12-15
Project Details
State
TX
County
Webb
Region
ERCOT
Developer
Gransolar Texas Two, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
80219 Lobo 345kV
Data Source
LBNL + Live