Cuchillas Solar — Project Summary

Queue ID
ERCOT-24INR0059
Capacity
305.6 MW
Technology
Solar
Status
active
Location
Webb, TX
Region
ERCOT
Developer
Gransolar Texas Two, LLC
IA Status
IA Executed

Cuchillas Solar

ERCOT-24INR0059BetaActiveSolarERCOTLBNL + Live

305.6 MW generation in Webb, TX · In queue since June 2021 · Proposed COD December 2028

305.6 MW

Capacity

1

Components

Solar

4y 10m

In Queue

IA Executed

IA Status

Signed Jun 2023

Interconnection Timeline

Queue → IA

2 years

IA → COD

5y 6m

Total Duration

2 years

Construction75%
Queue EntryJun 2, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementJun 20, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2028-12-15

Project Details

State

TX

County

Webb

Region

ERCOT

Developer

Gransolar Texas Two, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

80219 Lobo 345kV

Data Source

LBNL + Live