Briggs Storage
ERCOT-24INR0058BetaActiveBatteryERCOTLBNL + Live
70.39 MW storage in Haskell, TX · In queue since May 2021 · Proposed COD April 2028
70.39 MW
Capacity
1
Components
Battery
4y 11m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
6y 11m
Facilities Study50%
Queue EntryMay 31, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-04-15
Project Details
State
TX
County
Haskell
Region
ERCOT
Developer
Briggs Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 60515 Clear Crossing - 60507 Pendulo
Data Source
LBNL + Live
No news available for this project.