Pradera Solar
BetaActiveSolarERCOTLBNL + Live
118 MW generation in Webb, TX · In queue since July 2021 · Proposed COD March 2027
118 MW
Capacity
1
Components
Solar
4y 8m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5y 8m
Facilities Study50%
Queue EntryJul 8, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-03-31
Project Details
State
TX
County
Webb
Region
ERCOT
Developer
Pradera Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
tap 345 kV Lobo (80219) - Fowlerton (5709)
Data Source
LBNL + Live