Millers Branch Solar II
ERCOT-24INR0044BetaActiveSolarERCOTLBNL + Live
178 MW generation in Haskell, TX · In queue since November 2021 · Proposed COD May 2026
178 MW
Capacity
1
Components
Solar
4y 5m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
4y 6m
Facilities Study50%
Queue EntryNov 4, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-05-01
Project Details
State
TX
County
Haskell
Region
ERCOT
Developer
Miller's Branch Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 60703 Gauss - 60514 Clear Crossing (60712 QUASAR)
Data Source
LBNL + Live
No news available for this project.