Yaupon Solar SLF
ERCOT-24INR0042BetaActiveSolarERCOTLBNL + Live
204.08 MW generation in Milam, TX · In queue since March 2021 · Proposed COD July 2027
204.08 MW
Capacity
1
Components
Solar
5y 1m
In Queue
IA Executed
IA Status
Signed Sep 2023
Interconnection Timeline
Queue → IA
2y 6m
IA → COD
3y 10m
Total Duration
2y 6m
Construction75%
Queue EntryMar 30, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementSep 28, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-07-01
Project Details
State
TX
County
Milam
Region
ERCOT
Developer
Yaupon Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV Gibson Switch (3706) _x0013_ TNP One (39950)
Data Source
LBNL + Live
No news available for this project.