Rock N' Roll Solar SLF
BetaActiveSolarERCOTLBNL + Live
151.97 MW generation in Brazoria, TX · In queue since May 2021 · Proposed COD August 2027
151.97 MW
Capacity
1
Components
Solar
4y 10m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
6y 3m
Facilities Study50%
Queue EntryMay 10, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-08-30
Project Details
State
TX
County
Brazoria
Region
ERCOT
Developer
Rock N Roll Solar
Utility
—
Entity
ERCOT
Point of Interconnection
tap 138kV 44600 Rosharon - 44531 Winmil
Data Source
LBNL + Live
No news available for this project.