Percy Farm Solar
BetaActiveSolarERCOTLBNL + Live
198.63 MW generation in Matagorda, TX · In queue since March 2021 · Proposed COD May 2029
198.63 MW
Capacity
1
Components
Solar
5 years
In Queue
Facility Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
8y 2m
Facilities Study50%
Queue EntryMar 16, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-05-31
Project Details
State
TX
County
Matagorda
Region
ERCOT
Developer
Percy Farm Solar 1, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kV 8123 Blessing - 5915 STP
Data Source
LBNL + Live
No news available for this project.