Pinnington Solar
ERCOT-24INR0010BetaActiveSolarERCOTLBNL + Live
653.7 MW generation in Jack, TX · In queue since December 2020 · Proposed COD April 2026
653.7 MW
Capacity
1
Components
Solar
5y 4m
In Queue
IA Executed
IA Status
Signed Nov 2023
Interconnection Timeline
Queue → IA
2y 11m
IA → COD
2y 5m
Total Duration
2y 11m
Construction75%
Queue EntryDec 3, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementNov 2, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-04-30
Project Details
State
TX
County
Jack
Region
ERCOT
Developer
Hecate Energy Longhorn Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
1506 Long Hollow Switch 345kV
Data Source
LBNL + Live
No news available for this project.