Stem Solar
BetaActiveSolarERCOTLBNL + Live
200 MW generation in Swisher, TX · In queue since February 2020 · Proposed COD August 2025
200 MW
Capacity
1
Components
Solar
6y 1m
In Queue
Facility Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
5y 6m
Schedule
7 months past proposed COD
Facilities Study50%
Queue EntryFeb 4, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-08-26
Project Details
State
TX
County
Swisher
Region
ERCOT
Developer
Innovative Solar 134, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
tap 345kV 23914 Tule Canyon - 23912 Ogallala
Data Source
LBNL + Live
No news available for this project.