Cascabel Wind 2
ERCOT-23INR0561BetaActiveWindERCOTLBNL + Live
197.75 MW generation in Zapata, TX · In queue since March 2023 · Proposed COD December 2027
197.75 MW
Capacity
1
Components
Wind
3y 1m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 9m
Facilities Study50%
Queue EntryMar 13, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-01
Project Details
State
TX
County
Zapata
Region
ERCOT
Developer
Vaquero Wind Energy, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
345 kV Rapido Substation (New ETT Substation) tapping the existing 345 kV Line from CENIZO7C (#80225) to DELSOL7C (#80307).
Data Source
LBNL + Live