IEP Orchard BESS
9.99 MW storage in Fort Bend, TX · Proposed COD February 2025
9.99 MW
Capacity
1
Components
Battery
—
In Queue
IA Executed
IA Status
Signed Aug 2023
IA → COD
1y 6m
Schedule
13 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2025-02-28
State
TX
County
Fort Bend
Region
ERCOT
Developer
IEP Tejas Verde LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Station Name (TDSP Station Code): OR Load/Load Transformer Name :TR1 PTI BUS number: 44541 Voltage in kV (Transmission Level): 138 kV Project Size: 9.99 MW battery energy storage (BESS) system; 50 MWh connecting on CNP 34.5kV Distribution System.
Data Source
LBNL