Leakey BESS
BetaActiveBatteryERCOTLBNL
9.9 MW storage in Real, TX · In queue since November 2022 · Proposed COD February 2025
9.9 MW
Capacity
1
Components
Battery
3y 4m
In Queue
In Progress (unknown study)
IA Status
Signed Jan 2023
Interconnection Timeline
Queue → IA
2 months
IA → COD
2y 1m
Total Duration
2 months
Schedule
14 months past proposed COD
Construction38%
Queue EntryNov 29, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementJan 18, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2025-02-06
Project Details
State
TX
County
Real
Region
ERCOT
Developer
Regis Leaky LLC
Utility
—
Entity
ERCOT
Data Source
LBNL