Roadrunner Crossing BESS SLF
ERCOT-23INR0538BetaActiveBatteryERCOTLBNL + Live
40 MW storage in Eastland, TX · In queue since November 2022 · Proposed COD February 2026
40 MW
Capacity
1
Components
Battery
3y 5m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 3m
Schedule
2 months past proposed COD
Facilities Study50%
Queue EntryNov 15, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-02-13
Project Details
State
TX
County
Eastland
Region
ERCOT
Developer
Roadrunner Crossing BESS
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
68051 Reata 354kV
Data Source
LBNL + Live
No news available for this project.