Roadrunner Crossing BESS SLF — Project Summary

Queue ID
ERCOT-23INR0538
Capacity
40 MW
Technology
Battery
Status
active
Location
Eastland, TX
Region
ERCOT
Developer
Roadrunner Crossing BESS
IA Status
Facility Study

Roadrunner Crossing BESS SLF

ERCOT-23INR0538BetaActiveBatteryERCOTLBNL + Live

40 MW storage in Eastland, TX · In queue since November 2022 · Proposed COD February 2026

40 MW

Capacity

1

Components

Battery

3y 5m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 3m

Schedule

2 months past proposed COD

Facilities Study50%
Queue EntryNov 15, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-02-13

Project Details

State

TX

County

Eastland

Region

ERCOT

Developer

Roadrunner Crossing BESS

Utility

Entity

ERCOT

Service Type

Point of Interconnection

68051 Reata 354kV

Data Source

LBNL + Live