Torrecillas BESS
BetaActiveBatteryERCOTLBNL
9.9 MW storage in Webb, TX · Proposed COD May 2025
9.9 MW
Capacity
1
Components
Battery
—
In Queue
IA Executed
IA Status
Signed Jan 2015
Interconnection Timeline
IA → COD
10y 4m
Schedule
10 months past proposed COD
Construction75%
Queue Entry
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementJan 30, 2015
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2025-05-19
Project Details
State
TX
County
Webb
Region
ERCOT
Developer
Torrecillas Interconnect, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
161257 Torrecillas 345kV Station code: TORR
Data Source
LBNL